Two Machine Flow Shop Scheduler

Find a Johnson-rule job order minimizing makespan for a two-machine sequential flow shop.

Enter your values

01 / INPUT
Calculated on your device

YOUR CALCULATION

Result

—

Calculation steps

Work through one step at a time or reveal the complete calculation. The steps use your current inputs.

    How to calculate

    Apply Johnson’s partition-and-sort rule, then build both machines’ start and finish times.

    First group a≤b: ascending a; remaining group: descending b; M2start=max(M1finish,previous M2finish)

    Worked example

    Jobs A=(3,5),B=(6,2),C=(4,4) produce order A,C,B with makespan 15. The listed A,B,C order finishes at 17.

    Assumptions and input details

    Use 1–50 uniquely named jobs with nonnegative durations at most 1e9 in the chosen common unit. Every job is ready at time zero and visits machine 1 then machine 2; no preemption, setup time, transport, due date, blocking or limited intermediate buffer. One job at a time per machine, same order on both machines. Johnson’s makespan result applies to this model, not general multi-machine scheduling. Ties retain input order.

    References: UC Berkeley: Johnson algorithm assumptions

    Unit definitions

    Unit selection is independent of language. Each selector contains only units for its physical quantity. Calculations use defined base units internally.

    NIST measurement tables

    Using this calculator

    Can I enter my own problem?

    Yes. Replace the example values with your own inputs. The result, calculation steps, tables and applicable diagrams update from those inputs. Blank or invalid values clear the result; example values are never silently substituted for missing inputs.

    Are the results exact?

    Results use floating-point arithmetic and displayed rounding. Read the formula, assumptions and any stated data precision before interpreting the result.

    Is my input uploaded?

    The calculation runs in your browser. No account, file upload or external AI service is required. Inputs are not saved between page reloads.

    RELATED TOOL · PLANNINGCritical Path and Project Slack Calculator

    Calculate earliest and latest task times, total slack and critical tasks in a dependency network.

    RELATED TOOL · KITCHEN PLANNINGOven Tray Schedule Planner

    Assign entered tray occupancy times to identical simultaneous oven slots.

    RELATED TOOL · MATHEMATICSWork Rate Calculator

    Calculate how long two constant-rate workers, machines or pipes take together. Include an opposing drain and an already-completed fraction, with a progress graph.